Cape Town – Load shedding is set to be implemented from 16h00 on Sunday until 05:00 on Wednesday 20 April, Eskom announced in a statement on Sunday afternoon.
“The loss of four additional generation units at Matla, Tutuka, Duvha and Arnot power stations over the past 24 hours, exacerbated by the delay in units returning to service at Camden, Matla, Grootvlei and Tutuka power stations, has unfortunately necessitated the implementation of load shedding,” the power utility said in a statement.
Loadshedding will regretfully be implemented from 16:00 this afternoon until 05:00 on
Wednesday, 20 April, due to additional generation unit losses and delayed return to service of generators pic.twitter.com/NI1bTC8JzD— Eskom Hld SOC Ltd (@Eskom_SA) April 17, 2022
“The power system continues to be fragile and Eskom is forced to implement load shedding to manage and replenish emergency generation reserves, on which it has been relying to supply electricity this week.
“Since Friday afternoon, a generation unit each at Camden, Komati and Arnot power stations returned to service,” the power utility said.
Follow African Insider on Facebook, Twitter and Instagram
Source: AFP